Project Title    : Landscaping at Free zone
Location           : Free Zone Salalah
Client                 : Larsen and Toubro (L&T)
Work Detail     : Supply and fixing of Interlock and Curbstone.
Interlock total quantity 120,000 SQM and Curbstone total
quantity 90000 RM including road maintenance


Project Title         : Construction of Storage Yard.
Location                : Sohar
Client                      : Moon line trading and Co.
Work Detail          : Construction of workshop Shed with 45x20 SQM.
Three No offices, Two washrooms and carpentry, Car parking
and playing area.


Project Title        : EPC contract for Residential Villas
Location                : Awqad Salalah
Client                      : Prestige Investment Company LLC
Work Detail          : Construction of Double 6 Story residential Building
with total 305.2 SQM.


Project Title         : Construction of Chemical Lab
Location                : Muscat – Ghala Store
Client                      : RAY INTERNATIONAL LLC
Work Detail          : EPC contract for construction of
chemical Lab with full MEP works


Project Title         : Construction of Diesel Tanks
                                      Foundation including retaining wall
Location                : Khasab, Dibba & Lima Hospitals
Client                      : Ministry of Health
Work Detail         : Supply & Installation diesel Tanks
25K & 30K with construction of
foundations & retaining walls


Project Title          : Site Setup for Construction Company.
Client                       : Salalah Methanol Company
                                     (SNC-LAVALIN)
Location                 : University of Muscat, Muscat Oman
Work Detail           : Complete site setup for construction
company including Supply and Installation of Portacabin, Installation of PVC coated fencing
around the camp and reroute the services.


Project Title          : Civil Works Year-2018-19
Client                       : SEMBCORP Salalah Power & Water Company
Location                 : SEMBCORP Plant Taqah
Work Detail           :
1. Removing and construction of new concrete Slab in SWRO hall,
2. Construction of new concrete foundation around the 20000 L fuel diesel tank
3. Construction of new concrete road for booster pump area.
4. Partition Works & installation of Sandwich Panels in SWRO hall.
5. VAF system drainage installation with construction of foundation
6. Stone Pitching & Slop protection Works


Project Title        : Stone pitching at SMC
Location               : Salalah Methanol
Client                     : Peace Land Trade & Cont. Co. LLC
Work Detail         : Supply and Installation of 6521 SQ stone after bed preparation
and construction of 1052 sq concrete road at.


Project Title          : Construction of Diesel Tanks Foundation including retaining
Walls / bund Walls
Location                 : Al Haniyat Power & Water Plant
Client                       : RAECo SAOC
Work Detail           : Supply & Installation diesel Tanks 50K with construction
of foundations & retaining walls


Project Title          : Construction of Diesel Tanks Foundation including retaining
Walls / bund Walls
Location                 : Al Haniyat Power & Water Plant
Client                       : RAECo SAOC
Work Detail           : Supply & Installation diesel Tanks 50K with construction
of foundations & retaining walls